Anthropic Barber Lake: Cipher Mining data center in Colorado City, Texas
Project facts
- Developer or owner
- Cipher MiningEpoch AI,
- Tenant or user
- AnthropicEpoch AI,
- Planned power (Epoch AI estimate)
- 300 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $7.8 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- Colorado CityEpoch AI, citing Data Center Dynamics,
- County
- Mitchell CountyEpoch AI, citing Data Center Dynamics,
Where
Marked at the city centre its source gives. The ring marks Anthropic Barber Lake; the other pins are tracked projects in Texas.
Timeline
- Site grading and civil works begin.Epoch AI,
- Recorded as Site workEpoch AI,
- Foundations of Building 1 are visible.Epoch AI,
- Moved to Under constructionEpoch AI,
- Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north.Epoch AI,
More sources
- Cipher signs 168 MW AI hosting deal with Fluidstack, Google backs it (Sep 2025)
- Cipher adds 56 MW gross to reach 300 MW at Barber Lake (Nov 2025)
- Cipher 8-K exhibit: 207 MW total critical IT load (SEC, Nov 2025)
- Anthropic to expand use of Google Cloud TPUs (Oct 2025)
- Anthropic $50B US AI infrastructure with Fluidstack (Nov 2025)
- DCD: Cipher secures Fluidstack as customer, Google as investor
- Air quality permit listing 60 x 3 MW plus 60 x 3.1MW backup generators