Data center construction map: where data centers are being built in the U.S.
JOLT's data center construction map tracks 77 U.S. projects in 29 states with 43,403 MW of planned power: 1 in site work, 16 under construction and 60 operating. Texas leads with 8,934 MW, then Wisconsin and Ohio. Every record carries a dated source.
- Announced0
- Approved0
- Site work1
- Under construction16
- Operating60
- Planned MW43,403
Records as of . 77 projects in 29 states.
Map of U.S. data center projects
- Announced
- Approved
- Site work
- Under construction
- Operating
- Pin size: planned MW
Pins sit at each project's address, city or county as its source gives it. Interactive map tiles: OpenFreeMap, © OpenStreetMap contributors.
Every project on the map
- Amazon Madison Mega SiteCanton, MSOperating819 MW
- Amazon RidgelandRidgeland, MSOperating1,008 MW
- Anthropic Barber LakeColorado City, TXUnder construction300 MW
- Anthropic Lake MarinerBarker, NYOperating441 MW
- Anthropic-Amazon New CarlisleNew Carlisle, INOperating2,310 MW
- AWS BerwickBerwick, PAOperating212 MW
- AWS New AlbanyNew Albany, OHOperating405 MW
- Colossus 1Memphis, TNOperating442 MW
- Colossus 2Memphis, TNOperating2,065 MW
- Core42 Lake MarinerBarker, NYOperating58 MW
- CoreWeave Chester VAChester, VAOperating197 MW
- CoreWeave Dalton 1 & 2Dalton, GAOperating40 MW
- CoreWeave Denton TXDenton, TXOperating395 MW
- CoreWeave Ellendale NDEllendale, NDOperating520 MW
- Coreweave HeliosAfton, TXOperating800 MW
- CoreWeave Lancaster Greenfield siteLancaster, PAUnder construction124 MW
- CoreWeave Marble NCMarble, NCOperating91 MW
- CoreWeave Muskogee OKMuskogee, OKUnder construction181 MW
- Crusoe Abilene ExpansionAbilene, TXSite work941 MW
- GoodnightClaude, TXUnder construction1,294 MW
- Google ArcolaSterling, VAOperating93 MW
- Google BristowBristow, VAOperating286 MW
- Google Cedar RapidsCedar Rapids, IAUnder construction314 MW
- Google ColumbusColumbus, OHOperating464 MW
- Google Council Bluffs (East)Council Bluffs, IAOperating284 MW
- Google Fort WayneFort Wayne, INUnder construction1,035 MW
- Google Kansas City EastKansas City, MOOperating126 MW
- Google LancasterLancaster, OHOperating164 MW
- Google LincolnLincoln, NEOperating339 MW
- Google MesaMesa, AZOperating237 MW
- Google MidlothianMidlothian, TXOperating123 MW
- Google New AlbanyNew Albany, OHOperating400 MW
- Google OmahaOmaha, NEOperating474 MW
- Google PapillionPapillion, NEOperating284 MW
- Google Pryor (North)Pryor, OKOperating442 MW
- Google Red OakRed Oak, TXOperating185 MW
- Google Storey CountyStorey County, NVOperating389 MW
- Google The DallesThe Dalles, OROperating185 MW
- Meta AikenTrenton, SCOperating168 MW
- Meta Bowling GreenBowling Green, OHUnder construction570 MW
- Meta CheyenneCheyenne, WYOperating249 MW
- Meta Eagle MountainEagle Mountain, UTOperating179 MW
- Meta GallatinGallatin, TNOperating114 MW
- Meta HuntsvilleToney, ALOperating198 MW
- Meta HyperionHolly Ridge, LAUnder construction2,203 MW
- Meta JeffersonvilleJeffersonville, INOperating241 MW
- Meta KunaKuna, IDOperating198 MW
- Meta Los LunasLos Lunas, NMOperating273 MW
- Meta MontgomeryMontgomery, ALOperating465 MW
- Meta PrometheusNew Albany, OHOperating1,328 MW
- Meta RosemountRosemount, MNOperating241 MW
- Meta SarpySpringfield, NEOperating105 MW
- Meta TempleTemple, TXOperating231 MW
- Meta-QTS Hillsboro 2Hillsboro, OROperating243 MW
- Microsoft Fairwater AtlantaFayetteville, GAOperating859 MW
- Microsoft Fairwater WisconsinMount Pleasant, WIOperating2,715 MW
- Microsoft GoodyearGoodyear, AZOperating263 MW
- Microsoft Project OsmiumCumming, IAOperating228 MW
- Microsoft SAT14San Antonio, TXOperating66 MW
- Microsoft SAT40San Antonio, TXOperating106 MW
- Microsoft-Nebius New JerseyVineland, NJOperating70 MW
- OpenAI Stargate AbileneAbilene, TXOperating1,154 MW
- OpenAI Stargate LordstownWarren, OHUnder construction300 MW
- OpenAI Stargate MichiganSaline Township, MIUnder construction1,383 MW
- OpenAI Stargate MilamMilam County, TXUnder construction1,200 MW
- OpenAI Stargate New MexicoDoña Ana County, NMUnder construction2,450 MW
- OpenAI Stargate ShackelfordAbilene, TXUnder construction1,960 MW
- OpenAI Stargate WisconsinPort Washington, WIUnder construction1,300 MW
- QTS Cedar RapidsFairfax, IAUnder construction1,587 MW
- QTS Eagle MountainEagle Mountain, UTUnder construction411 MW
- QTS Richmond 1Sandston, VAOperating333 MW
- QTS Richmond 2Sandston, VAOperating252 MW
- QTS Richmond 3Sandston, VAOperating336 MW
- STACK Infrastructure NVA02Manassas, VAOperating487 MW
- Stream PhoenixGoodyear, AZOperating267 MW
- Vantage TX1San Antonio, TXOperating179 MW
- xAI QTS AtlantaAtlanta, GAOperating24 MW
New this week
No project was announced or moved to a new stage in the seven days to . The newest change on record is below.
What changed
The latest 50 stage changes and dated notes, newest first, each with its source.
- Meta Aiken, Trenton, SC. Building 2 is operational assuming a 3 month lag compared to Building 1.Epoch AI,
- Anthropic Lake Mariner, Barker, NY. Building 2 is operational.Epoch AI, citing investors.terawulf.com,
- QTS Cedar Rapids, Fairfax, IA. Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared.Epoch AI,
- Google Pryor (North), Pryor, OK. Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.Epoch AI,
- CoreWeave Denton TX, Denton, TX. Building 8 interior fit-out scheduled to begin.Epoch AI, citing tdlr.texas.gov,
- Meta Prometheus, New Albany, OH. Buildings 7-10 are operational, based on infrared drone video from RAAD captured on this date.Epoch AI,
- Coreweave Helios, Afton, TX. Building 1 operational at full capacity.Epoch AI, citing investor.galaxy.com,
- Meta Gallatin, Gallatin, TN. Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.Epoch AI,
- Google Fort Wayne, Fort Wayne, IN. Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning.Epoch AI,
- Meta Aiken, Trenton, SC. Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans.Epoch AI,
- AWS Berwick, Berwick, PA. Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it.Epoch AI,
- Anthropic Barber Lake, Colorado City, TX. Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north.Epoch AI,
- Meta Bowling Green, Bowling Green, OH. Roofs of Buildings 1 and 2 are more than halfway complete.Epoch AI, citing archive.ph,
- OpenAI Stargate Lordstown, Warren, OH. Active construction visible on and around the datacenter, with the roofing mostly in place.Epoch AI,
- Meta Los Lunas, Los Lunas, NM. Building 2 shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months.Epoch AI,
- OpenAI Stargate Abilene, Abilene, TX. Buildings 5-8 are structurally complete and roofed but not yet confirmed operational.Epoch AI,
- OpenAI Stargate Wisconsin, Port Washington, WI. Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.Epoch AI,
- Anthropic Lake Mariner, Barker, NY. Building 1 looks complete, consistent with it going operational back in May.Epoch AI,
- Core42 Lake Mariner, Barker, NY. Both buildings still operational according to satellite imagery.Epoch AI,
- CoreWeave Lancaster Greenfield site, Lancaster, PA. Cooling install continues on the roof, satellite imagery indicates that not all units have been completed.Epoch AI,
- Microsoft-Nebius New Jersey, Vineland, NJ. Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating.Epoch AI,
- xAI QTS Atlanta, Atlanta, GA. No significant change to the building since the August 2025 image.Epoch AI,
- CoreWeave Denton TX, Denton, TX. Buildings 1-7 are operational and running, with no construction work visible.Epoch AI, citing d1io3yog0oux5.cloudfront.net,
- Google Midlothian, Midlothian, TX. Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.Epoch AI,
- CoreWeave Ellendale ND, Ellendale, ND. According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.Epoch AI,
- OpenAI Stargate New Mexico, Doña Ana County, NM. Construction has advanced significantly since February 2026.Epoch AI,
- Coreweave Helios, Afton, TX. Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work.Epoch AI,
Data center projects by state
Each state links to its page, with that state's projects by stage and a map. For every data center an industry tracker counts in each state, see data centers under construction by state.
| State | Projects | Not yet operating | Planned MW |
|---|---|---|---|
| Texas | 14 | 5 | 8,934 |
| Wisconsin | 2 | 1 | 4,015 |
| Ohio | 7 | 2 | 3,631 |
| Indiana | 3 | 1 | 3,586 |
| New Mexico | 2 | 1 | 2,723 |
| Tennessee | 3 | 0 | 2,621 |
| Iowa | 4 | 2 | 2,413 |
| Louisiana | 1 | 1 | 2,203 |
| Virginia | 7 | 0 | 1,984 |
| Mississippi | 2 | 0 | 1,827 |
| Michigan | 1 | 1 | 1,383 |
| Nebraska | 4 | 0 | 1,202 |
| Georgia | 3 | 0 | 923 |
| Arizona | 3 | 0 | 767 |
| Alabama | 2 | 0 | 663 |
| Oklahoma | 2 | 1 | 623 |
| Utah | 2 | 1 | 590 |
| North Dakota | 1 | 0 | 520 |
| New York | 2 | 0 | 499 |
| Oregon | 2 | 0 | 428 |
| Nevada | 1 | 0 | 389 |
| Pennsylvania | 2 | 1 | 336 |
| Wyoming | 1 | 0 | 249 |
| Minnesota | 1 | 0 | 241 |
| Idaho | 1 | 0 | 198 |
| South Carolina | 1 | 0 | 168 |
| Missouri | 1 | 0 | 126 |
| North Carolina | 1 | 0 | 91 |
| New Jersey | 1 | 0 | 70 |
Largest data center projects in the U.S.
The 25 largest by planned MW. Planned power is Epoch AI's estimate where Epoch AI is the source.
- 1Microsoft Fairwater WisconsinMount Pleasant, WI · Operating · Microsoft2,715 MW
- 2OpenAI Stargate New MexicoDoña Ana County, NM · Under construction · Oracle2,450 MW
- 3Anthropic-Amazon New CarlisleNew Carlisle, IN · Operating · Amazon2,310 MW
- 4Meta HyperionHolly Ridge, LA · Under construction · Meta2,203 MW
- 5Colossus 2Memphis, TN · Operating · SpaceXAI2,065 MW
- 6OpenAI Stargate ShackelfordAbilene, TX · Under construction · Oracle1,960 MW
- 7QTS Cedar RapidsFairfax, IA · Under construction1,587 MW
- 8OpenAI Stargate MichiganSaline Township, MI · Under construction · Oracle1,383 MW
- 9Meta PrometheusNew Albany, OH · Operating · Meta1,328 MW
- 10OpenAI Stargate WisconsinPort Washington, WI · Under construction · Oracle1,300 MW
- 11GoodnightClaude, TX · Under construction1,294 MW
- 12OpenAI Stargate MilamMilam County, TX · Under construction · Softbank1,200 MW
- 13OpenAI Stargate AbileneAbilene, TX · Operating · Oracle1,154 MW
- 14Google Fort WayneFort Wayne, IN · Under construction · Google1,035 MW
- 15Amazon RidgelandRidgeland, MS · Operating · Amazon1,008 MW
- 16Crusoe Abilene ExpansionAbilene, TX · Site work · Microsoft941 MW
- 17Microsoft Fairwater AtlantaFayetteville, GA · Operating · Microsoft859 MW
- 18Amazon Madison Mega SiteCanton, MS · Operating · Amazon819 MW
- 19Coreweave HeliosAfton, TX · Operating · CoreWeave800 MW
- 20Meta Bowling GreenBowling Green, OH · Under construction · Meta570 MW
- 21CoreWeave Ellendale NDEllendale, ND · Operating · CoreWeave520 MW
- 22STACK Infrastructure NVA02Manassas, VA · Operating487 MW
- 23Google OmahaOmaha, NE · Operating · Google474 MW
- 24Meta MontgomeryMontgomery, AL · Operating · Meta465 MW
- 25Google ColumbusColumbus, OH · Operating · Google464 MW
Developers with more than one project
Download the data
Every project, with each fact's source link and date, free under CC BY 4.0 with attribution.
Cite as
JOLT Mobile Offices & Containers, "U.S. data center construction projects," November 5, 2026, joltrents.com, CC BY 4.0. Includes data from Epoch AI, "Data on AI data centers," CC BY 4.0.
Includes data from Epoch AI, Data on AI data centers, used under CC BY 4.0. JOLT rewrote Epoch AI's status notes as one sentence each and added dated company, state, county and utility sources.
Site offices for this build
Site offices for U.S. data center builds
The Grid: badge-ready 40 ft container site offices, delivered to any U.S. data center site by DC Deploy, quoted per campus.

Grid Core
- Monthly
- $3,250/mo
- On site in
- 6–8 weeks
- Delivery to your site
- DC Deploy, quoted per campus

Grid Command
- Monthly
- $4,250/mo
- On site in
- 6–8 weeks
- Delivery to your site
- DC Deploy, quoted per campus
Questions about the map
Where are data centers being built in the U.S.?
The map tracks 77 projects in 29 states. By planned power the largest totals are in Texas (8,934 MW), Wisconsin (4,015 MW), Ohio (3,631 MW), Indiana (3,586 MW) and New Mexico (2,723 MW). 17 projects in 11 states are not yet operating.
How many data centers are under construction in the U.S.?
Of the 77 projects on the map, 16 are under construction, 1 are in site work, 0 are approved, 0 are announced and 60 are operating. The count covers the projects with a public, dated source, not every building in the country; the state table on the under-construction-by-state page counts every site an industry tracker lists.
What are the largest data center projects in the U.S.?
By planned power: Microsoft Fairwater Wisconsin in Mount Pleasant, WI (2,715 MW, operating), OpenAI Stargate New Mexico in Doña Ana County, NM (2,450 MW, under construction) and Anthropic-Amazon New Carlisle in New Carlisle, IN (2,310 MW, operating). The table on this page ranks the largest 25.
Where does the data come from?
The records start from Epoch AI's open data on AI data centers (CC BY 4.0), U.S. sites only, pulled weekly, and add company and developer releases, state economic development releases, county planning and permit records and utility filings. Each fact on a project page carries its source link and date. A value with no source reads "Not announced".
What do the stages mean?
Announced: a company or public body has named the project. Approved: a zoning, permit or incentive vote has passed. Site work: clearing, grading or utility work has started. Under construction: building construction has started. Operating: at least one building is running. Each project page lists every stage change with its date and source.
How current is the map?
The newest dated record on this page is from November 5, 2026. Epoch AI's data is pulled every week and new sources are added as they are published; the pages are rebuilt from the records each time the site is published.
Can I download the data?
Yes. Every project is in a CSV and a JSON file, free under CC BY 4.0 with attribution, at joltrents.com/data/data-center-projects.csv and joltrents.com/data/data-center-projects.json. The files keep each fact's source link and date.
Can I get the list by email?
Yes. Enter an email address in the field on this page to get the weekly data center build list every Monday: new projects and stage changes. Each project page also has a field to get one email when that project changes. Every email has a one-click unsubscribe link.