Meta Kuna: data center in Kuna, Idaho
Project facts
- Tenant or user
- MetaEpoch AI,
- Planned power (Epoch AI estimate)
- 198 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $5.8 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Idaho Power CompanyEpoch AI,
- City
- KunaEpoch AI,
- County
- Ada CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Meta Kuna; the other pins are tracked projects in Idaho.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed.Epoch AI,
- Moved to Under constructionEpoch AI,
- Building 1 and 2 are operational.Epoch AI,
- Moved to OperatingEpoch AI,
More sources
- Official Pamphlet from Meta
- Application for Power Purchase Agreement, Pleasant Valley Solar 1
- Application for Power Purchase Agreement, Pleasant Valley Solar 2
- Approval to move start date of Solar 2 to May 31, 2026
- staff comments
- Notice of Application for 3rd PPA (Blacks Creek Energy Center)
- Idaho Statesman: Peak construction reached in March 2025
- Idaho Statesman: Expected water usage reported in 2022