Core42 Lake Mariner: data center in Barker, New York
Project facts
- Developer or owner
- Core42Epoch AI,
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 58 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $2.2 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- BarkerEpoch AI,
- County
- Niagara CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Core42 Lake Mariner; the other pins are tracked projects in New York.
Timeline
- Land clearing begins for Building 1, also known as CB-1, the first large AI/HPC building on the site.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 is operational.Epoch AI, citing investors.terawulf.com,
- Moved to OperatingEpoch AI,
- Buildings 1 and 2 both appear to have complete building and cooling equipment, based on satellite imagery.Epoch AI, citing investors.terawulf.com,
- Building 2 is operational.Epoch AI, citing investors.terawulf.com,
- Both buildings still operational according to satellite imagery.Epoch AI,
More sources