Microsoft Fairwater Wisconsin: data center in Mount Pleasant, Wisconsin
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 2,715 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $85.7 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- WE EnergiesEpoch AI,
- City
- Mount PleasantEpoch AI,
- County
- Racine CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Microsoft Fairwater Wisconsin; the other pins are tracked projects in Wisconsin.
Timeline
- Land clearing begins for Building 1.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building.Epoch AI,
- Moved to Under constructionEpoch AI,
- Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet.Epoch AI,
- Building 1 is operational.Epoch AI, citing x.com,
- Moved to OperatingEpoch AI,
- The main shell of Building 2 looks almost completed.Epoch AI, citing mtpleasantwi.gov,