OpenAI Stargate Wisconsin: Oracle data center in Port Washington, Wisconsin
Project facts
- Tenant or user
- OpenAIEpoch AI,
- Planned power (Epoch AI estimate)
- 1,300 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $34.2 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- Port WashingtonEpoch AI, citing Vantage Data Centers,
- County
- Ozaukee CountyEpoch AI, citing Vantage Data Centers,
Where
Marked at the city centre its source gives. The ring marks OpenAI Stargate Wisconsin; the other pins are tracked projects in Wisconsin.
Timeline
- Ground broken for the facility, land clearing begins for all buildings.Epoch AI,
- Recorded as Site workEpoch AI,
- Land clearing continues, foundation construction clearly begins for eastern and northern buildings.Epoch AI,
- Moved to Under constructionEpoch AI,
- Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.Epoch AI,