xAI QTS Atlanta: SpaceXAI data center in Atlanta, Georgia
Project facts
- Tenant or user
- SpaceXAIEpoch AI,
- Planned power (Epoch AI estimate)
- 24 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $656 millionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- AtlantaEpoch AI,
- County
- Fulton CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks xAI QTS Atlanta; the other pins are tracked projects in Georgia.
Timeline
- X Corp's $700 million investment in AI training hardware for the Atlanta data center is approved by the Development Authority of Fulton County.Epoch AI, citing developfultoncounty.com,
- Recorded as Under constructionEpoch AI,
- XAI's GPU cluster in the QTS Atlanta building at 1025 Jefferson Street NW is operational around this time.Epoch AI, citing businessinsider.com,
- Moved to OperatingEpoch AI,
- No significant change to the building since the cluster became operational.Epoch AI,
- No significant change to the building since the August 2025 image.Epoch AI,