Microsoft Fairwater Atlanta: data center in Fayetteville, Georgia
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 859 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $24.1 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Georgia PowerEpoch AI,
- City
- FayettevilleEpoch AI,
- County
- Fayette CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Microsoft Fairwater Atlanta; the other pins are tracked projects in Georgia.
Timeline
- Land clearing begins for southern part.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 and 2 are operational.Epoch AI, citing news.microsoft.com,
- Moved to OperatingEpoch AI,
- Building 4 roof is complete and all mechanical equipment appears to be installed.Epoch AI,
- Building 4 still has some equipment strewn around the perimeter, so we think it is still going through commissioning.Epoch AI,
- Building 3 and 4 are operational.Epoch AI,