QTS Cedar Rapids: data center in Fairfax, Iowa
Project facts
- Developer or owner
- Not announced
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 1,587 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $42.9 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Alliant EnergyEpoch AI,
- City
- FairfaxEpoch AI,
- County
- Linn CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks QTS Cedar Rapids; the other pins are tracked projects in Iowa.
Timeline
- Land clearing begins for Building 1-3.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 roof complete, with air-cooled chillers in place.Epoch AI,
- Moved to Under constructionEpoch AI,
- Based on satellite imagery, the Buildings 1-3 shells look complete.Epoch AI,
- Similar to April, Buildings 1-3 shells look complete.Epoch AI,
- Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared.Epoch AI,
More sources