Google Cedar Rapids: data center in Cedar Rapids, Iowa
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 314 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $9.9 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- Cedar RapidsEpoch AI,
- County
- Linn CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Google Cedar Rapids; the other pins are tracked projects in Iowa.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 cooling towers and generators starting to be put in place.Epoch AI,
- Moved to Under constructionEpoch AI,
- About half of Building 1 generators are in place.Epoch AI,
- Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction.Epoch AI,