Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 197 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $4.3 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- ChesterEpoch AI,
- County
- Chesterfield CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks CoreWeave Chester VA; the other pins are tracked projects in Virginia.
Timeline
- Conversion starts at CTP-01.Epoch AI,
- Recorded as Under constructionEpoch AI,
- Building 1's second data hall scheduled to come online this month.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 1 is scheduled to be fully online by this point, so we count the full 27 MW as operational here.Epoch AI,
- Satellite imagery shows Building 1 complete, with Building 2's yard work and early construction visible.Epoch AI,
- Based on satellite imagery, Building 3 has cleared its land and is beginning construction.Epoch AI,