Project facts
- Tenant or user
- Anthropic, Cursor, SpaceXAIEpoch AI,
- Planned power (Epoch AI estimate)
- 2,065 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $58 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- MemphisEpoch AI,
- County
- Shelby CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Colossus 2; the other pins are tracked projects in Tennessee.
Timeline
- Land clearing begins next to the existing building.Epoch AI,
- Recorded as Site workEpoch AI,
- Battery facility connected to the building.Epoch AI,
- Moved to Under constructionEpoch AI,
- Battery facility looks complete.Epoch AI, citing sec.gov,
- Moved to OperatingEpoch AI,
- Since October, an array of dry cooling air-cooled condensers has been added, and appears almost complete.Epoch AI,
- The first array of dry cooling air-cooled condensers for Building 1 has been completed and is operational.Epoch AI, citing sec.gov,
- The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power".Epoch AI, citing sec.gov,