Meta Montgomery: data center in Montgomery, Alabama
Project facts
- Tenant or user
- MetaEpoch AI,
- Planned power (Epoch AI estimate)
- 465 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $13.6 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Hensel PhelpsEpoch AI,
- Utility or energy company
- Not announced
- City
- MontgomeryEpoch AI,
- County
- Montgomery CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Meta Montgomery; the other pins are tracked projects in Alabama.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 and 2 under construction, with all chillers visible.Epoch AI,
- Moved to Under constructionEpoch AI,
- Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation.Epoch AI,
- Buildings 1 and 2 are operational.Epoch AI,
- Moved to OperatingEpoch AI,