Meta Sarpy: data center in Springfield, Nebraska
Project facts
- Tenant or user
- MetaEpoch AI,
- Planned power (Epoch AI estimate)
- 105 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $3 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- SpringfieldEpoch AI,
- County
- Sarpy CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Meta Sarpy; the other pins are tracked projects in Nebraska.
Timeline
- Building 1 grading underway.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 shell, electrical and cooling equipment looks complete, with minimal construction work, so we expect it to be operational within 3 months.Epoch AI,
- Moved to Under constructionEpoch AI,
- Building 1 is operational.Epoch AI,
- Moved to OperatingEpoch AI,