Google Omaha: data center in Omaha, Nebraska
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 474 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $15 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- OmahaEpoch AI,
- County
- Douglas CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Google Omaha; the other pins are tracked projects in Nebraska.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 2 has 3 cooling towers installed.Epoch AI,
- Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed.Epoch AI,
- Confirmation that there's no obvious construction happening for Building 2.Epoch AI,
- Confident that Building 2 is operational.Epoch AI,
- Building 3 has all backup generators in place but they are still being installed.Epoch AI,
- Building 3 appears almost complete, with only minimal construction work and equipment remaining.Epoch AI,
- Building 3 is operational.Epoch AI,
More sources