CoreWeave Ellendale ND: data center in Ellendale, North Dakota
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 520 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $15.2 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- EllendaleEpoch AI,
- County
- Dickey CountyEpoch AI,
- State
- North DakotaEpoch AI,
Where
Marked at the address its source gives. The ring marks CoreWeave Ellendale ND; the other pins are tracked projects in North Dakota.
Timeline
- Start of construction for the first building, according to Applied Digital.Epoch AI, citing ir.applieddigital.com,
- Recorded as Site workEpoch AI,
- CoreWeave signed the first lease package for 250 MW.Epoch AI, citing sec.gov,
- Moved to Under constructionEpoch AI,
- A new 150 MW lease brings CoreWeave to 400 MW total contracted.Epoch AI, citing ir.applieddigital.com,
- The first 50 MW slice of Building 1 has reached Ready for Service status according to this report.Epoch AI, citing ir.applieddigital.com,
- Moved to OperatingEpoch AI,
- This Applied Digital report says the rest of Building 1 has reached Ready for Service, bringing the first building to its expected 100 MW.Epoch AI, citing ir.applieddigital.com,
- According to satellite imagery, Building 1 looks complete and in service, with the surrounding power/cooling equipment also operational.Epoch AI,
- According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed.Epoch AI,
More sources