Project facts
- Tenant or user
- MetaEpoch AI,
- Planned power (Epoch AI estimate)
- 2,203 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $61.8 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- MortensonEpoch AI,
- Utility or energy company
- EntergyEpoch AI,
- City
- Holly RidgeEpoch AI,
- County
- Richland ParishEpoch AI,
Where
Marked at the city centre its source gives. The ring marks Meta Hyperion; the other pins are tracked projects in Louisiana.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Foundations are underway for the main buildings, and the overall layout aligns with the architectural renderings published in 2025.Epoch AI, citing engineering.fb.com,
- Moved to Under constructionEpoch AI,
- Building 1 and 2 roof is finished and cooling is at an advanced stage of installation.Epoch AI,