Microsoft Goodyear: data center in Goodyear, Arizona
Project facts
- Tenant or user
- MicrosoftEpoch AI,
- Planned power (Epoch AI estimate)
- 263 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $7.7 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- GoodyearEpoch AI,
- County
- Maricopa CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Microsoft Goodyear; the other pins are tracked projects in Arizona.
Timeline
- Land clearing begins for Building 1.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 operational.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 2 operational.Epoch AI,
- Building 3 and 4 operational.Epoch AI,
- Confirmation that Building 3 and 4 look complete.Epoch AI,
- Foundations appear to be underway for Building 5 and 6, just north of Building 4.Epoch AI,