Goodnight: data center in Claude, Texas
Project facts
- Developer or owner
- Not announced
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 1,294 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $38.1 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Crusoe, HoffmanEpoch AI,
- Utility or energy company
- SerenaEpoch AI,
- City
- ClaudeEpoch AI,
- County
- Not announced
Where
Marked at the city centre its source gives. The ring marks Goodnight; the other pins are tracked projects in Texas.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 and 2 under construction.Epoch AI,
- Moved to Under constructionEpoch AI,
- Construction on Building 1 and 2 looks about halfway to completion.Epoch AI,
- Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures.Epoch AI,
More sources
- Amended tax abatement agreement, with updated blueprints on p.46
- Original tax abatement agreement, with original blueprints and specs on the last page
- TABS database, with "Llano" data centers in the city of Claude
- Press release reports Google investing in a new data center in Armstrong County
- Clean Air Act Initial Prevention of Significant Deterioration permit application.