Microsoft-Nebius New Jersey: data center in Vineland, New Jersey
Project facts
- Developer or owner
- NebiusEpoch AI,
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 70 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $1.9 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- VinelandEpoch AI,
- County
- Cumberland CountyEpoch AI,
- State
- New JerseyEpoch AI,
Where
Marked at the address its source gives. The ring marks Microsoft-Nebius New Jersey; the other pins are tracked projects in New Jersey.
Timeline
- Land clearing begins for northern two buildings.Epoch AI,
- Recorded as Site workEpoch AI,
- By mid-December 2025 the building was still not complete.Epoch AI,
- Moved to Under constructionEpoch AI,
- High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase.Epoch AI, citing newsletter.semianalysis.com,
- Moved to OperatingEpoch AI,
- Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating.Epoch AI,
More sources
- Nebius: up to 300 MW capacity at new New Jersey data center
- DataOne and Nebius partner for 300 MW AI data center (Data Centre Magazine)
- Microsoft secures 100,000 NVIDIA GB300 via Nebius deal (Tom's Hardware)
- DataOne CEO on first 50 MW delivery to Nebius (LinkedIn)
- Large data center nears completion in Vineland (Cape May County Herald)
- SemiAnalysis: Stop Saying Half of 2026 US Datacenter Capacity Is Canceled