Google New Albany: data center in New Albany, Ohio
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 400 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $12.6 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- New AlbanyEpoch AI,
- County
- Not announced
Where
Marked at the city centre its source gives. The ring marks Google New Albany; the other pins are tracked projects in Ohio.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 is operational.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 2 is operational.Epoch AI,
- Building 3 is operational, based on all cooling units and tanks installed, minimal construction work around the building.Epoch AI,
- Building 4 is operational, based on all cooling units and tanks installed, minimal construction work around the building.Epoch AI,
- Water vapor from cooling towers is present across Building 1-4, confirming their operation.Epoch AI,
- Building 5 has more cooling towers installed but not complete, and the roof is almost complete.Epoch AI,
- Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building.Epoch AI,
More sources