Google Lancaster: data center in Lancaster, Ohio
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 164 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $5.2 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- LancasterEpoch AI,
- County
- Fairfield CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Google Lancaster; the other pins are tracked projects in Ohio.
Timeline
- Land clearing in progress for the site.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 operational.Epoch AI, citing earth.google.com,
- Moved to OperatingEpoch AI,
- Building 2 is close to completion.Epoch AI,
- Building 2 operational.Epoch AI,
- At this point, Building 1 and 2 have since already been operational.Epoch AI,