Google Pryor (North): data center in Pryor, Oklahoma
Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 442 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $13.9 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- PryorEpoch AI,
- County
- Mayes CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Google Pryor (North); the other pins are tracked projects in Oklahoma.
Timeline
- Land clearing begins for Building 1.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 is operational, based on default roof-to-operational time.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 2 is being retrofitted from a warehouse.Epoch AI,
- The new substation for Building 2 looks mostly complete, half of the cooling towers are installed.Epoch AI,
- Building 2 looks almost complete, but still appears to have three cooling towers missing.Epoch AI,
- Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.Epoch AI,