AWS Berwick: Amazon data center in Berwick, Pennsylvania

Operatingsince Epoch AI,

Project facts

Developer or owner
AmazonEpoch AI,
Tenant or user
Not announced
Planned power (Epoch AI estimate)
212 MWEpoch AI,
Announced investment
Not announced
Capital cost (Epoch AI estimate)
$6.4 billionEpoch AI,
Acres
Not announced
Buildings
Not announced
General contractor
Not announced
Utility or energy company
Not announced
City
BerwickEpoch AI,
County
Luzerne CountyEpoch AI,
State
PennsylvaniaEpoch AI,

Where

AWS Berwick, Berwick, PA: Operating, 212 MWCoreWeave Lancaster Greenfield site, Lancaster, PA: Under construction, 124 MW

Marked at the address its source gives. The ring marks AWS Berwick; the other pins are tracked projects in Pennsylvania.

Timeline

  1. Land clearing begins.Epoch AI, citing datacenterdynamics.com,
  2. Recorded as Site workEpoch AI,
  3. Cumulus completes a 48 MW, 300,000 sq ft powered shell for the first data center at the Susquehanna campus.Epoch AI, citing prnewswire.com,
  4. Moved to Under constructionEpoch AI,
  5. AWS acquires the Cumulus/Talen building campus for $650M.Epoch AI, citing sec.gov,
  6. Building 1 fit out and related construction begins under Amazon, based on the Susquehanna River Basin Commission schedule.Epoch AI, citing srbc.gov,
  7. Building 1 operational estimate.Epoch AI, citing earth.google.com,
  8. Moved to OperatingEpoch AI,
  9. Building 2 operational estimate.Epoch AI, citing pacodeandbulletin.gov,
  10. The SRBC increases approved water use from 0.060 MGD to 0.129 MGD.Epoch AI, citing srbc.gov,
  11. Buildings 1 and 2 visibly complete and operational.Epoch AI,
  12. Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it.Epoch AI,

More sources

Site offices for this build

Site offices for AWS Berwick, Pennsylvania

The Grid: badge-ready 40 ft container site offices, delivered to Pennsylvania by DC Deploy, quoted per campus.

Talk to a data center specialist

Other projects within 50 miles

No other tracked project is within 50 miles of Berwick.

See every project on the data center construction mapData centers under construction in Pennsylvania

Includes data from Epoch AI, Data on AI data centers, used under CC BY 4.0. JOLT rewrote Epoch AI's status notes as one sentence each and added dated company, state, county and utility sources.