Project facts
- Tenant or user
- Google DeepMindEpoch AI,
- Planned power (Epoch AI estimate)
- 286 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $9 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- BristowEpoch AI,
- County
- Prince William CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Google Bristow; the other pins are tracked projects in Virginia.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Building 1 is operational, based off of colored motion artifacts from cooling towers.Epoch AI,
- Moved to OperatingEpoch AI,
- Building 2 is operational, based off it being at least 12 months since the roof was complete.Epoch AI,
- Building 3 is operational, based off of colored motion artifacts from cooling towers.Epoch AI,