Meta Rosemount: data center in Rosemount, Minnesota
Project facts
- Tenant or user
- MetaEpoch AI,
- Planned power (Epoch AI estimate)
- 241 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $6.7 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- RosemountEpoch AI,
- County
- Dakota CountyEpoch AI,
Where
Marked at the address its source gives. The ring marks Meta Rosemount; the other pins are tracked projects in Minnesota.
Timeline
- Land clearing begins.Epoch AI,
- Recorded as Site workEpoch AI,
- Both buildings and their cooling infrastructure look complete, but the site probably is likely still under commissioning, and few cars are parked to the right of Building 1.Epoch AI,
- Moved to Under constructionEpoch AI,
- Buildings 1 and 2 are estimated to be operational.Epoch AI,
- Moved to OperatingEpoch AI,