Project facts
- Tenant or user
- Not announced
- Planned power (Epoch AI estimate)
- 124 MWEpoch AI,
- Announced investment
- Not announced
- Capital cost (Epoch AI estimate)
- $3.5 billionEpoch AI,
- Acres
- Not announced
- Buildings
- Not announced
- General contractor
- Not announced
- Utility or energy company
- Not announced
- City
- LancasterEpoch AI,
- County
- Lancaster CountyEpoch AI,
- State
- PennsylvaniaEpoch AI,
Where
Marked at the address its source gives. The ring marks CoreWeave Lancaster Greenfield site; the other pins are tracked projects in Pennsylvania.
Timeline
- Coreweave announces $6 billion investment into Lancaster data centers, at two former printing press sites.Epoch AI, citing investors.coreweave.com,
- Recorded as Under constructionEpoch AI,
- Cooling install continues on the roof, satellite imagery indicates that not all units have been completed.Epoch AI,